- 2012 Arthur T. Everham Safety Award
- Member DCA, PLCA, MEA
- OQ Compliant through NCCER, Veriforce, MEA
Case Studies
Case Study: HDD Pipe Extraction (Video Content)
Monday, April 18, 2016
When it comes to repairing a pipe drilled in by horizontal drilling methods operators are sometimes left with few options. On a recent Ohio project a right-of-way corridor was very congested with existing pipe that had been drilled in. This 12" pipe, all 0.500' wall, had been in the ground for many years. One pipe in particular was showing signs of internal and external problems. These problems were significant enough to cause the operator to make the decision to replace the pipe. No room existed for a new drill. The only option was an extraction.
Rigging, note pencil (top L). Five part blocks rigged (top R).
Block close up weight (10,000lbs) (bottom C).
Extracting 2,400' of 12" pipe requires detailed planning and flawless execution. Still there is risk in the operation. Setting 68 tons of steel pipe in motion is very much a matter of accurate and proper attachment of the rigging and percussion equipment, and the gentle application of force. There is a choreography to the extraction process. The successful application of 200,000 pounds of force to a 2,400' pipe previously bored into the earth depends on skilled hands that are very easy on the throttles. Finesse wins every time over brute strength. The Grundorams supplied by TT Technologies (See http://www.tttechnologies.com/) are sized for the project.The hammer speed can be varied from 50 to 180 strokes per minute. The attachment requirements are very precise, the angle of extraction is equally precise. The accuracy of alignment will preserve the weld joints much longer into the process.
Tension alone will not come close to moving a 68 ton mass of steel pipe or overcome the friction forces of the pipe's wall against the earth. But the combination of tension and the judicious application of percussive force can add sufficient power and vibration to overcome the inertia of the pipe's mass. Tension force prevents the mass from reverting to its original position and allows any movement to be maintained when applying percussive force. This combination of a point force combined with a steady pull actually imparts movement to the pipe mass and once in motion it becomes easier to maintain the movement. It is thought that some liquifaction of the old drilling mud may take place at the pipe wall to soil interface. This also aids the process of extraction by imparting energy into the old drilling mud causing it to act as a lubricant.
Grundoram supported for pull (L) Attaching load cell to cable (R)
In this project two air hammers, two five part steel blocks on sleds, and two D8 CATS, applying a combined force of over 186,000 pounds of force were utilized to make the pipe move. After movement began the force rapidly diminshed to 52,000 lbs as the pipe was withdrawn. The air hammers were only used at 25-30% throttle. It was enough to do the job.
Of course the other advantage of pipe extraction is the fact that the new pipe can be welded up in advance, hydro-tested and pulled in by welding it to the old pipe. This is exactly what we did to give our customer a new hydrotested pipe ready to be placed into service.
Grundoram connected (L) Track Hoes repositioning Grundoram (C) Grundoram ready for next pull (L)
Missteps could have occurred during this project. The extraction pipe could have failed in place, the pipe could have been distorted and become wedged in place, the welds could have separated. The only guarantee of success is proper planning and careful execution.
Our team consisted of Midwestern Contractors, Laney Directional Drilling (http://www.laneydrilling.com/) and TT Technologies (http://www.tttechnologies.com).
Project Notes:
- Extraction pipe consisted of 2,400' of 12" 0.500" wall
- Replacement pipe consisted of 2,400' of 12" 0.500" wall
- Total welds = 60 requiring 7 passes for each weld
- Additional welds required to join 0.717" wall to 0.500" for Grundoram air hammers
- Pipe string weight approximately 68 tons
- Two Grundoram Air Hammers and casings
- Two five part steel blocks mounted on sleds
- Two D8 Cats
- Two Cat 336E excavators
- Extraction rate 400'/day (Limited work space, pipe had to be cut and the pull reset)
Storm rolling into project site
Project Safety Notes:
- Spring weather conditions
- High winds, cold temperatures, thunderstorms lightening
- Site conditions were dangerous with mud and standing water a constant challenge
- High energy potentials generated when tension was applied to the rigging
- Heavy machinery moving in tight quarters
- Industrial location with heavy truck and rail traffic
- Overpasses caused overhead obstructions
- Many in-ground utilities requiring hydro-excavation
No incidents or accidents occured on this project. The entire team functioned as a unit with the work and safety planning and project execution.
Three views of drill string
View of completed tie-in with expansion joint and thrust block
Midwestern Contractors works throughout the Midwestern States. Our geographical footprint includes Ohio, Pennsylvania, Indiana, Kentucky, Tennessee, Illinois, Missouri, Kansas, Nebraska, Iowa, Minnesota, Wisconsin, Michigan. This case study illustrates the planning, and team work required to successfully work on critical assets. We value the confidence our customers place in us to carry out projects like this one. A sincere thank you to our superintendents, foremen, crews, Laney crews and TTTechnologies' consultants for a job well done.
Thanks to Ztylus for the 4:1 iPhonography equipment used in this article see www.Ztylus.com
View our case studies to get a better insight on how we do business and how we can help you on your next project.
- Safety - Achieving the Goal of Zero Accidents
- Pipeline Lowering
- LNG Maintenance Project
- Natural Gas Interconnect & Meter Station
- Natural Gas Meter & Regulator Station
- Upgrading a Gas Injection Field
- HDD Pipe Extraction (Video Content)
- 1400' Horizontal Directional Drill Project (Video Content)
- 130th Bridge
- Suspended Pipelines
- The Cost of Regulation
A legacy of responsibility.
For over 60 years, we have built an environment within our company where safety is everyone’s responsibility. In all phases of every project, we accept nothing less than an accident-free jobsite. We believe that having a safe workplace leads to a productive workplace, and we’re dedicated to having the highest level of protection for our employees, our customers and the general public.
Learn More- 1.5 million miles of pipeline constructed
- 1,500 pump, compressor & meter stations built
- 7.6 million feet of gas distribution lines
- 120,000 man hours per year of integrity work
Project Map

60 years of experience in the natural gas and petroleum industry
Look over our project map. If your projects are located in this area we can help you with any type of Pipeline, Station, Distribution or Maintenance work.
Learn More Contact Us